How to paint a room in the right order

Paint a room from the top down: ceiling first, then walls, then doors, frames and skirtings. Give everything its first coat in that order, then the second coat in the same order. Always roll into paint that is still wet, so that no lines show.

The order of work

Working from the top down means drips and spatters land on surfaces you have not painted yet.

  1. The ceiling: cut in, then roll.
  2. The walls: cut in along the ceiling, corners, frames and skirtings, then roll, one wall at a time.
  3. The frames, doors and skirtings last, with enamel.

Cutting in

Cutting in is the brush work along edges.

Rolling walls and ceilings

Doors, frames and skirtings

Doors and trims are handled the most, so they get hard-wearing enamel.

Plan the day around drying times

The tin gives a recoat time. Plan around it so that you are never waiting with nothing to do. While one surface dries, paint another.

In the book's example the paint recoats after 2 hours. A painter who starts at 08:00 gets two coats on the ceiling and walls, and a first coat of water-based enamel on the door and frame, by 16:30.

Check each wall while it is wet

When you finish a wall, stand in the corner and look along it towards the window. Light from the side shows every lap mark, thin patch and missed spot. Fix them while the paint is wet.

Painting in a home where people live

This guide is based on Chapter 8 of House Painting as a Side Hustle in South Africa.